   New outbuilding under construction

Storage shed for Design & Technology

 
       
  Wednesday 20 June - Wood sorted after delivery.  Now we need some dry weather!   Wednesday 27 June Day 1 - a week later and weather forecast still doubtful.  It's now or never.   First timbers positioned  
 
       
  Next row of timbers - you can start to see where the doors will go   The ends of each timber are cut so that they just slot together   Using a rubber mallet to make sure that the corner joints are tight  
       
  Far end timbers stacked in more convenient position   Ayrton worked so hard clearing the site before he was given the chance to help build shed   More timbers added  
       
  The shed going up really quickly at this stage   Pupils come out to check on progress   So Technology teacher shows off just how easy this cabin type structure is to build!   
       
 

Easy to see size of door opening now it has timbers above

 

Cut timbers where window will be

 

You can see size of window now it has timber above

 
       
 

3 heavy roof timbers in position

 

Construction at end of day 1 - time running out and weather closing in

 

Cover in position to protect from rain - but timbers still need treating with preservative

 
       
 

End of day 1 - all of exterior wood treated and shed covered - rain forecast for next 24 hours

 

Thursday 28 June - Day 2 - later in day all roof boards fixed and ready for felt

 

First strip of roofing felt fixed

 
       
 

Before second strip of felt is put on a layer of adhesive must be applied on overlap

 

Time up at end of a short working second day

 

Friday 29 June - Covers removed, site tidied and shed looking good in rare sunshine

 
       
 

A final look inside before being closed up for weekend rain that has been forecast

 

Most of roofing felt fixed after another short working day

 

Monday 2 July - A few more hours spent completing felting and fixing end fascias

 
     

 

 

 

Watch this space!

More photos when work resumes 

 
 

Friday 6 July - Cedar left over from new build used to clad supplied double door frames

 

From the outside looking almost finished in the early evening sunshine

 

 

 